F-Q43 Premises RWC Patrol Checklist
File Reference : | F-Q43 Premises RWC Patrol Checklist |
Premises checklist that can be completed by Responsible Welding Coordinator (RWC) as part of evidence of ongoing inspection and monitoring for demonstrating compliance with CE / UKCA marking BS EN 1090 Factory Production Control (FPC) system.
This checklist also includes a section with Health & Safety checks which can be removed if not required and then lists the various checks completed by the RWC on;
- Measuring Equipment
- Welding Consumables
- Parent Materials
- Equipment / Calibration register
- Welder qualifications
- Weld procedures
- Production checks / paperwork
- NDT testing / Inspection
The checklist is setup for these checks to be logged each month and covering 12 months and may be supported by more frequent and detailed inspections.